The construction of Pohang Accelerator Laboratory X-ray Free-Electron Laser (PAL-XFEL), a 0.1-nm hard X-ray free-electron laser (FEL) facility based on a 10-GeV S-band linear accelerator (LINAC), is achieved in Pohang, Korea by the end of 2016. The construction of the 1.11 km-long building was completed by the end of 2014, and the installation of the 10-GeV LINAC and undulators started in January 2015. The installation of the 10-GeV LINAC, together with the undulators and beamlines, was completed by the end of 2015. The commissioning began in April 2016, and the first lasing of the hard X-ray FEL line was achieved on 14 June 2016. The progress of the PAL-XFEL construction and its commission are reported here.