Next Article in Journal
Factors Influencing Stakeholders’ Decision to Invest in Residential Properties: A Perceptual Analysis of Flood-Risk Areas
Next Article in Special Issue
Nonlinear Stress-Free-State Forward Analysis Method of Long-Span Cable-Stayed Bridges Constructed in Stages
Previous Article in Journal
Analysis of Carbon Emission Reduction Paths for the Production of Prefabricated Building Components Based on Evolutionary Game Theory
Previous Article in Special Issue
The Current Development of Structural Health Monitoring for Bridges: A Review
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Application of Bayesian Update Method in the Construction Control of Continuous Rigid Frame Bridge Girders with High Piers and Large Spans

1
School of Civil Engineering and Architecture, Wuhan Institute of Technology, Wuhan 430073, China
2
Hubei Provincial Engineering Research Center for Green Civil Engineering Materials and Structures, Wuhan 430073, China
3
School of Urban Construction, Hubei Business College, Wuhan 430079, China
*
Authors to whom correspondence should be addressed.
Buildings 2023, 13(6), 1556; https://doi.org/10.3390/buildings13061556
Submission received: 19 May 2023 / Revised: 8 June 2023 / Accepted: 17 June 2023 / Published: 19 June 2023

Abstract

:
In the construction process of large-scale bridges, there are uncertainties and time-varying factors in the environment and construction loads. It is difficult to make accurate estimates of the theoretical calculation models of construction control in advance. In view of this situation, Bayesian dynamic updating method is introduced to re-estimate the predicted results of the theoretical model. When applying this method, first, the finite element calculation model is determined based on the response surface method, and its calculation results are used as prior information. Then, combined with the actual detection data during the construction process, the Bayesian update formula is derived based on the conjugate prior distribution to correct the theoretical prediction results of bridge construction monitoring. Finally, the actual stress detection data of the control section of high-pier and large-span continuous rigid frame bridges during the construction process illustrate the application process of Bayesian updating in improving the theoretical prediction model. Results indicate that the internal force of the bridge control section obtained by re-evaluating by Bayesian theory not only incorporates the priori information models but also actual monitors sample information during the construction process. The predicted results reflect the true deformation and stress state of the bridge during the bridge construction process and improve the precision of construction monitoring.

1. Introduction

With its advantages of convenient construction, reasonable force transmission and strong crossing ability, high-pier and long-span continuous rigid-frame bridges have become an important bridge type for crossing ravines and canyons in the southwestern mountainous regions of China [1,2]. The internal forces and deformations of the structure are the main control indicators during the cantilever construction process of continuous rigid-frame bridges, ensuring the reasonable completion of the bridge [3,4,5,6]. In existing bridge construction control, the results of finite element simulation analysis are widely used as the expected values for construction control [7,8]. However, due to various factors during the construction stage of bridges such as environmental conditions, material properties, geometric defects and physical parameter errors, the predicted results of finite element analysis for continuous rigid-frame bridges are frequently inconsistent with the actual construction state of the bridge [8,9,10]. To improve control accuracy, scholars both domestically and internationally have conducted effective research on bridge construction control theories and technologies. Zhang [11], Liu [12], and Liu [13] introduced grey theory into the assessment of bridge construction states. Ren [8] and Niu [14] proposed a finite element model updating method for bridges based on response surface methodology. Wang [15] and Bai [16] developed a deflection prediction model for continuous rigid-frame bridges based on the MEC-BP neural network. Sarwar [17], Xin [18], Chen [19], Cho [20], and Zhang [21] applied Kalman filtering estimation to predict the structural deformation in bridge construction. Innocenzi [22] established an improved bridge fine-scale finite element analysis model by using shell elements for all members in ANSYS. Nicoletti [23] calibrates the analytical model by building a digital twin model and continuously changing the structural input parameters of AM according to the current state of the bridge. These research results, which update the theoretical analysis model from the aspects of mathematical methods, refined finite element models, and digital twin models, have updated the theoretical analysis models and significantly improved the accuracy of bridge construction monitoring and prediction results. the numerous factors that can influence the calculation results of theoretical models for bridges such as environmental temperature, prestress loss, shrinkage, creep, and elastic modulus are characterized by their variability and time dependence. Although the above method can establish the finite element analysis model more accurately, the parameter correction of the theoretical calculation model cannot take into account all the influencing factors at the same time. Therefore, in order to predict the control indicators and parameters during bridge construction, it is necessary to find a method that can minimize the effects of these multi-factor uncertainties. Bayesian theory provides a method for an effective solution to this contradiction [24,25,26,27,28,29,30]. The basic idea [31,32] of Bayesian theory for parameter prediction is to emphasize the collection of prior information to form a prior distribution, make full use of existing sample observations, and then use Bayesian updates to combine prior information and actual sample observations to improve statistical forecast quality.
In the construction process of continuous rigid-frame bridges, the finite element analysis results of cross-sectional internal forces, despite potential deviations due to parameter variations or errors, can still reflect the patterns of real results. These calculation results can be used as prior information for predictions [33,34,35]. In this paper, Bayesian updating is applied to calculate and dynamically predict the internal forces and deformations of the control sections of high-pier and long-span continuous rigid-frame bridges based on the results of finite element model calculations and field monitoring data.

2. Determination of Internal Forces and Prior Information Model in Bridge Construction Sections

2.1. Preliminary Determination of a Priori Information of Internal Forces in Cross-Section

Continuous rigid-frame bridges with high piers and long spans are mainly cast with cantilever hanging baskets and self-erected section by section symmetrically. Due to the large spans, the cantilever construction causes obvious deflection. However, due to the high rigidity of this type of bridge, it is difficult to adjust the geometric alignment of the cantilever structure after the completion of construction. Therefore, it is essential to analyze the primary construction monitoring indicators and their influencing factors for the high-pier and long-span continuous rigid-frame bridge before and during construction and develop solutions in advance. Compared to the geometric monitoring of bridges, monitoring internal forces within the cross-section is more challenging and subject to a greater number of uncertain factors. Deviations in internal forces not only affect the geometric alignment of the structure but can also have severe implications for its safety, potentially leading to strength or instability failure in continuous rigid-frame bridges. This section primarily introduces the preliminary determination methods for the a priori information of internal forces in bridge construction.
Considering the characteristics of high-pier and long-span continuous rigid-frame bridges, the prior information of the section internal force in bridge construction can be determined through a forward analysis method and verified through a backward analysis method. When the forward analysis method determines the prior information of the control index, the finite displacement theory is mainly used for stage cycle analysis currently, and the calculation results are relatively accurate [36]. However, it is important to keep in mind the following five points to guarantee accurate results for the construction process analysis:
  • The actual construction process and procedures should be strictly followed in the bridge structure forward analysis.
  • The backward analysis based on the results of the actual construction should be used to determine the initial state of the structural analysis.
  • The initial state of each stage analysis should be based on the results of the previous construction stage.
  • The forward analysis procedure should gradually take the time lag effects such as concrete shrinkage, creep, prestress, and temperature, into account.
  • The finite element model used in the forward analysis needs to be accurate enough to accurately represent the current state of the continuous rigid-frame bridge.

2.2. Modification of a Priori Information Model for Bridge Construction Cross-Sectional Internal Forces

In order to accurately reflect the structural characteristics of the high-pier and long-span continuous rigid frame bridge, the finite element model established based on the design drawings must be modified to take into account the effects of construction errors, model simplification, and parameter changes. The model modification can use the finite element model modification method based on the response surface methodology [37,38,39], whose basic principle is to select appropriate structural parameters and responses within a reasonable range of structural parameters, and fit response surface models between structural parameters and structural responses by calculating the response at sample points by varying parameter values within the design space. Taking the measured response as the target, the response surface model is used to replace the initial finite element model for parameter optimization, and finally the final correction value and correction model of the parameters are obtained.
Figure 1 depicts the specific process of the finite element model modification.
The calculation results of cross-sectional internal forces obtained by the modified finite element analysis model can serve as the prior information for controlling the internal forces at various sections during bridge construction.
Figure 2 depicts the method for determining the prior information of the internal forces of bridge sections.

3. Correction and Prediction of Construction Monitoring Results for Continuous Rigid Frame Bridges

According to the central limit theorem [40,41], if variables follow similar distributions and have weak correlations, their means will approximately follow a normal distribution. There are many factors that affect the internal forces characteristics of continuous rigid frame bridges during construction such as environmental temperature, elastic modulus of concrete materials, shrinkage and creep, section size, construction loads, and concrete compactness. These factors are independent of each other and their detection results follow an approximately normal distribution during the bridge construction. Therefore, the random distribution model of predicted results for the internal forces of the bridge section can be considered to follow a normal distribution. The statistical parameters (variance σ2 and mean value μ) of on-site test samples for the section internal forces of the rigid frame bridge are not constant during different construction stages. Additionally, the variance of prior samples cannot be determined when dynamically updating and predicting detection data for the first time. Consequently, when using Bayesian theory to estimate the section of internal forces of the rigid frame bridge during the construction process (i.e., correcting the theoretical calculation results for both), it is necessary to take into account two working conditions. The first condition involves predicting the posterior distribution of the mean when both the sample variance and mean are unknown, while the second one involves predicting the posterior distribution of the mean when the variance is known.

3.1. Bayesian Estimation When Population Sample Mean and Variance Are Unknown

The detection samples of section stress during the bridge construction process are denoted as x1, x2, x3, , xn. It is assumed that they are drawn from the population sample N (θ, σ2), and both θ and σ2 are unknown. The prior distributions for θ and σ2 can be taken as normal-inverse-gamma prior [42], i.e., θ|σ2~N (μ, σ2/k), σ2~Γ1(r/2, λ/2), where μ, k, r, λ are known hyperparameters. Equation (1) represents the likelihood function of (θ, σ2).
l ( θ , σ 2 | x ) σ n exp { 1 2 σ 2 [ i = 1 n ( x i x ¯ ) 2 + n ( x ¯ θ ) 2 ] }
The joint density of the normal-inverse-gamma prior distribution for (θ, σ2) is shown in Equation (2) [43]:
π ( θ , σ 2 ) = π 1 ( θ | σ 2 ) π 2 ( θ | σ 2 ) ( σ 2 ) [ ( r + 1 ) / 2 + 1 ] exp { 1 / ( 2 σ 2 ) [ k ( θ μ ) 2 + λ ] }
According to Equations (1) and (2), the joint posterior density of parameters θ and σ2 is shown in Equation (3):
π ( θ , σ 2 | x ) l ( θ , σ 2 | x ) π ( θ , σ 2 ) ( σ 2 ) r + n + 1 2 + 1 exp { 1 2 σ 2 [ ( n 1 ) s 2 + λ + H ] }
where
H = n ( x ¯ θ ) 2 + k ( θ μ ) 2 = ( n + k ) ( θ n x ¯ + k μ n + k ) 2 + n k n + k ( x ¯ μ ) 2
If vn = n + r, kn = n + k, Equation (3) could be obtained by transformation:
π ( θ , σ 2 | x ) ( σ 2 ) ν n + 1 2 + 1 e 1 2 σ 2 [ ( ν n σ n 2 + k n ( θ μ ( x ¯ ) ) 2 ]
where
μ ( x ¯ ) = n x ¯ + k μ n + k ν n σ n 2 = ( n 1 ) s 2 + λ + n k n + k ( x ¯ μ ) 2
According to Equations (4) and (5), when both the mean and variance of the population sample are unknown, Equation (5) can be used to predict the internal forces during the construction process of the continuous rigid-frame bridge. In Equation (5), μ( x ¯ ) represents the predicted or adjusted result of the internal forces of the bridge during the construction process at time t, which μ can be understood as the theoretical solution obtained by numerical analysis or theoretical calculation at time t, x ¯ is the mean value of the on-site detection sample, k is the prior degree of freedom of θ, which is determined by the confidence level of the prior information and can be set to the sample size of the first detection data, and n is the actual number of detection samples, which can be set to the sample size at time t or the number of samples in the second detection.

3.2. Bayesian Estimation When Population Sample Variance Is Known

The population samples of section stress are denoted as X~(θ, σ2), where σ2 is known, while θ is unknown. The prior distribution π(θ) of θ obeys N(μ, τ2), where μ and τ2 are determined through statistical analysis of the actual monitoring results of cross-sectional stress at time t (second monitoring).
Therefore, for the posterior distribution π(θ|x) of θ,
π ( θ | x ) f ( x | θ ) π ( θ ) exp { 1 2 [ ( x θ ) 2 σ 2 + ( θ μ ) 2 τ 2 ] }
If ρ = 1/τ2 + 1/σ2,
π ( θ | x ) exp { ρ 2 [ θ 1 ρ ( μ τ 2 + x σ 2 ) ] 2 }
μ ( x ) = 1 ρ ( μ τ 2 + x σ 2 ) = σ 2 σ 2 + τ 2 μ + τ 2 σ 2 + τ 2 x
It is evident that, when σ2 is known, given mean μ and variance τ2 of the prior information, the accurate values of the internal forces in bridge construction can be predicted using Equation (8), where x is obtained through numerical calculation or theoretical solution.
Additionally, if the third inspection sample x1, , xn at time t + 1 follows the normal distribution N(θ, σ2), the joint density of x = (x1, …, xn) is represented by Equation (9):
f ( x | θ ) = ( 2 π σ 2 ) n / 2 exp { 1 2 σ 2 i = 1 n ( x i θ ) 2 }
In Equation (7), when x is replaced by x ¯ ( x ¯ is the mean value of samples x1, …, xn, i.e., the mean value of on-site detection samples), and σ2 is replaced by σ2/n, the posterior distribution π(θ|x) of θ can be obtained as follows:
π ( θ | x ) = 1 2 π η n exp { 1 2 η n 2 [ θ μ n ( x ¯ ) ] 2 }
where
μ n ( x ¯ ) = σ 2 / n σ 2 / n + τ 2 μ + τ 2 σ 2 / n + τ 2 x ¯ η n 2 = σ 2 τ 2 n τ 2 + σ 2
Based on Equations (10) and (11), it is possible to predict the internal forces of a continuously rigid frame bridge during the construction process, given the variance σ2 of the population sample, using Equation (11). In Equation (11), μn( x ¯ ) represents the predicted or adjusted results of internal forces at time t during the construction process of the continuously rigid frame bridge. σ2 can be obtained through statistical analysis of the initial inspection sample. τ2 and n represent the variance and sample size of the second inspection sample, respectively. μ is the theoretical solution obtained by theoretical calculation or numerical analysis at time t, and x ¯ is the mean value of the second inspection sample.

3.3. Bayesian Update of Construction Monitoring Indexes for Continuous Rigid Frame Bridges

From the perspective of Bayesian prediction theory, Equation (5) provides the revised value or prediction value of the mean μ(x) when the population sample mean and variance (θ and σ2) cannot be accurately determined, based on the prior sample mean μ or theoretical calculated value. Equation (11) provides the mean value μ(x) based on the prior sample mean μ (or theoretical calculated value) and the information of the detection sample (sample size n and sample mean x ¯ ), when the population sample variance σ2 is known and the mean value θ is unknown.
By analyzing Equations (5) and (11), it can be concluded that in the process of bridge construction monitoring, the predicted values of the internal forces of the section can be represented as weighted results of the detection sample mean and theoretical calculated results. When the variance and mean are unknown, the weighting factors for the detection sample mean and theoretical calculated result are, respectively, the following: k/(n + k) and n/(n + k). When the variance is known, the weighting factors for the detection sample mean and theoretical calculated result are, respectively, the following: σ2/n/(σ2/n + τ2) and τ2/(σ2/n + τ2). To standardize the expression, if λ1 = n/(n + k) or λ2 = τ2/(σ2/n + τ2), Equation (5) can be transformed into the following: μ( x ¯ ) = λ1 x ¯ + (1 − λ1)μ = μ + λ1( x ¯ μ), Equation (11) can be transformed into: μn( x ¯ ) = (1 − λ2)μ + λ2 x ¯ = μ + λ2( x ¯ μ). Hence, the Bayesian update model at a future time can be expressed as the following:
μ i ( x ¯ ) = μ + λ i ( x ¯ 0 μ 0 )
where i = 1 or 2, and they represent the two working conditions of Equations (5) and (11), respectively. In these equations, μi( x ¯ ) represents the predicted value of the section stress of the section of the high-pier and long-span continuous rigid structure bridge in a certain construction stage. x ¯ 0 represents the mean of the detected sample of the section stress at time t0. μ0 represents the predicted value of the prior model of internal force at time t0. μ represents the predicted results of the section stress at time t obtained through finite element analysis. When using Equation (12) to modify the monitoring results during the construction process, the key lies in determining the weighting coefficients λi. For the condition of unknown variance, according to the existing statistical results, the value of k can be the number of samples required to satisfy a certain confidence level condition, while n can be selected corresponding to the number of samples for the sample mean x ¯ . Additionally, based on statistical analysis of multiple previous monitoring results, the existing sample variance can be approximated as the population sample variance, allowing the use of λ2 for Bayesian prediction. In this case, σ2 can be calculated using Equation (13), and n and τ2 represent the sample size and variance, respectively, corresponding to the monitoring samples.
σ 2 = σ ^ 2 = 1 n i = 1 n ( x i x ¯ ) 2
Figure 3 illustrates the updating process of concrete carbonation depth based on Bayesian method.

4. Analysis of a Calculation Example

The new prediction model, which is based on Bayesian theory, takes into account the calculation results of the original theoretical model as well as the results of the on-site monitoring data collected throughout the construction process. To illustrate the process of using Bayesian theory to predict the theoretical data of construction monitoring indicators for high-pier and large-span continuous rigid-frame bridges and examine its effectiveness, this paper introduces and analyzes the construction monitoring results of two stress control sections of the Qingshuijiang high-pier and large-span continuous rigid-frame bridge on the Kaixi Ring Expressway in Guizhou Province.

Project Overview

The Qingshuijiang Bridge is located in the northern section of the Kaili Ring Expressway in Guizhou Province. The main span of the bridge is a prestressed concrete continuous rigid frame bridge with a length of (81 + 150 + 150 + 81) m. The route is divided into sections, and the left and right sections are structurally independent. The height of the main pier is 112 m, and the box beam adopts a variable cross-section single-box flat section. Considering that the main factors affecting the stress state of a large-span prestressed concrete continuous rigid-frame bridge are the sectional stress of the piers and main beams, this paper takes the stress test results of the 5# pier Section 2-2 (the cantilever root section of the main beam) and the 6# pier Section 4-4 (the main beam L/4 section) after pouring and tensioning in each section of the top plate as examples for analysis, and the application of Bayesian updating in the dynamic prediction of construction control indicators of high-pier and large-span continuous rigid-frame bridges is explained in detail. Figure 4 depicts the longitudinal layout of the main beam stress (strain) test section.
The numbering of the cantilever construction beam sections for the main beam is shown in Figure 5.
During the construction monitoring process of this project, two Bayesian updates were conducted for stress prediction of the 5# pier Section 2-2 and 6# pier Section 4-4. The first Bayesian update for the 5# pier Section 2-2 was conducted after the completion of casting and tensioning block 1, and the second update was conducted after the completion of block 6. The first Bayesian update for the 6# pier Section 4-4 was conducted after the completion of casting and tensioning block 9, and the second update was conducted after the completion of block 12. Figure 6 depicts the stress monitoring points for each section. The stress values of the top plates at control Sections 2-2 and 4-4 during cantilever construction of the main girder are shown in Table 1, and the data in the table represent the average measured values of the two stress measurement points on the top plate.
The Bayesian estimate weight coefficients at various stages can be obtained by thoroughly analyzing all the stress monitoring data of Sections 2-2 and 4-4 under various construction conditions, as shown in Table 2.
Figure 7, Figure 8, Figure 9 and Figure 10 show the predicted curves of the theoretical calculation results for Sections 2-2 and 4-4 after Bayesian updating. They are compared to the theoretical results and actual test values. The predicted curve for the stress values at Section 2-2 (4-4) after the first Bayesian update was determined by modifying the model based on the detected data after pouring and tensioning of block 1# (9#). The predicted curve of the second Bayesian update was determined after model correction based on the detection data obtained after pouring and tensioning of block 6# (12#).
From Figure 7, Figure 8, Figure 9 and Figure 10, conclusions could be observed as follows: (1) There is a large discrepancy between the control section stress obtained directly from the initial finite element calculation model and the actual measured stress during the construction process, especially for Section 2-2 (main beam root section). The error in stress increases as the construction segment progresses, and the maximum error reaches 16.25% (after pouring) and 15.87% (after prestressing). (2) The predicted curve after Bayesian updating is in good agreement with the development law of the theoretical analysis prediction curve, and the prediction result becomes closer to the measured value after each Bayesian model update, which can better reflect the stress state of the control section. (3) The model’s accuracy of prediction can be significantly increased following each Bayesian update. For example, for Section 2-2, the error between the measured value and theoretical value of section stress monitored after concrete prestressing was reduced from 15.87% to 12.21% and 7.75% under the conditions of no Bayesian update and once and double Bayesian update, respectively. For Section 4-4, the error was reduced from 10.47% to 6.80% and 4.25%, respectively. The above analysis results show that the Bayesian update that integrates theoretical models and actual measured data has a good prediction effect. It is necessary to introduce Bayesian updating to re-evaluate the calculation results of conventional theoretical models in light of the construction environment of high-pier and long-span continuous rigid frame bridges and the numerous uncertain factors that affect the bridge stress state.

5. Conclusions

In order to reduce the theoretical calculation error of the control indicators for construction monitoring of continuous rigid-frame bridges with high piers and long spans, research on parameter re-estimation based on Bayesian theory was carried out.
  • A Bayesian update method is established under the condition that the prior information sample mean and variance are unknown, as well as that the prior information sample variance is known but the mean value is unknown. The prediction formula for the sample mean value can be adopted as Equations (5) and (11), respectively. Bayesian update can quickly reduce the error between theoretical prediction results and measured values, and better prediction results can be achieved after fewer times of Bayesian updates.
  • The estimation of bridge construction monitoring and control indicators based on Bayesian updating simultaneously integrates prior information and detection information obtained during the actual construction process. The prediction curve is consistent with the theoretical calculation curve, and the prediction results can more accurately reflect the stress and linear state during the bridge construction process.
  • The finite element calculation model corrected based on the response surface method has better prior information, higher prediction effect and efficiency, and requires fewer updates to achieve higher prediction accuracy.
  • The results of the finite element analysis of cross-sectional stresses at various sections during bridge construction follow a similar pattern to the measured values after two rounds of Bayesian updates. The prediction accuracy and efficiency are significantly increased as a result of the error being cut in half. These research results can serve as a theoretical basis for the construction control of continuous rigid-frame bridges.

Author Contributions

Conceptualization, X.Z.; supervision, X.Z. and L.C.; writing—original draft, X.Z., T.D. and J.C.; data curation, Q.Y.; writing—review and editing, L.C., T.D. and J.G.; software, A.L. and J.C.; methodology, L.C.; investigation, W.F. All authors have read and agreed to the published version of the manuscript.

Funding

This work is partially supported by the National Natural Science Foundation of China (Grant No. 52178300), Graduate Innovative Fund of Wuhan Institute of Technology (Grant No. CX2022205).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data presented in this study are available on request from the corresponding author.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Yang, B. Research and practice of construction monitoring for long-span continuous beam bridges. Railw. Stand. Des. 2012, 56, 61–64. [Google Scholar]
  2. Lu, Z.Y. Stability analysis of high-pier large-span continuous rigid-frame bridge during construction. Railw. Constr. Technol. 2021, 28, 119–122, 135. [Google Scholar]
  3. Kang, C.J.; Schneider, S.; Wenner, M.; Marx, S. Development of design and construction of high-speed railway bridges in Germany. Eng. Struct. 2018, 163, 184–196. [Google Scholar] [CrossRef]
  4. Gou, H.; Long, H.; Bao, Y.; Chen, G.; Pu, Q.; Kang, R. Stress distributions in girder-arch-pier connections of long-span continuous rigid frame arch railway bridges. J. Bridge Eng. 2018, 23, 04018039. [Google Scholar] [CrossRef]
  5. Yuan, Z.; Ng, P.L.; Bačinskas, D.; Du, J. Analysis of non-uniform shrinkage effect in box girder sections for long-span continuous rigid frame bridge. Balt. J. Road Bridge Eng. 2018, 13, 146–155. [Google Scholar] [CrossRef]
  6. Yang, X.P.; Zhao, J.X. Research on line shape and stress control during cantilever construction of high-pier large-span continuous rigid-frame bridge. J. Shandong Agric. Univ. (Nat. Sci. Ed.) 2021, 52, 525–528. [Google Scholar]
  7. Cheng, X.-X. Model updating for a continuous concrete girder bridge using data from construction monitoring. Appl. Sci. 2023, 13, 3422. [Google Scholar] [CrossRef]
  8. Ren, W.-X.; Chen, H.-B. Finite element model updating in structural dynamics by using the response surface method. Eng. Struct. 2010, 32, 2455–2465. [Google Scholar] [CrossRef]
  9. Pan, Z.A.F.; Fu, C.C.; Jiang, Y. Uncertainty analysis of creep and shrinkage effects in long-span continuous rigid frame of sutong bridge. J. Bridge Eng. 2011, 16, 248–258. [Google Scholar] [CrossRef]
  10. Zhu, J.Y.; Gu, S.; Yan, A.X. Sensitivity analysis of construction monitoring parameters for high-pier large-span PC continuous rigid-frame bridge. J. Southwest Univ. Sci. Technol. 2018, 33, 37–40. [Google Scholar]
  11. Zhang, X.C. Research on monitoring technology and application of ultra-long tied-arch bridge construction. Railw. Constr. Technol. 2022, 29, 117–121. [Google Scholar]
  12. Liu, X.; Yi, X.; Wang, B.; Liu, Y. Condition assessment of grouped cable forces of cable-stayed bridge using deflection data. Buildings 2023, 13, 472. [Google Scholar] [CrossRef]
  13. Liu, Q.C.; Wang, Y.Z.; An, J.J.; Liu, S.B.; Zhang, T. Application of Markov residual-corrected grey theory model in construction monitoring of continuous beam bridges. J. China Foreign Highw. 2017, 37, 170–173. [Google Scholar]
  14. Niu, J.; Zong, Z.H.; Chu, F.P. Damage identification method of girder bridges based on finite element model updating and modal strain energy. Sci. China-Technol. Sci. 2015, 58, 701–711. [Google Scholar] [CrossRef]
  15. Wang, X.D.; Miao, C.Q.; Wang, X.M. Prediction analysis of deflection in the construction of composite box-girder bridge with corrugated steel webs based on MEC-BP neural networks. Structures 2021, 32, 691–700. [Google Scholar] [CrossRef]
  16. Bai, Y.T.; Wang, X.M.; Lu, Z.Y.; Zhang, J.D. Intelligent construction control of wave-shaped steel diaphragm continuous rigid-frame bridge erection. J. Build. Sci. Eng. 2022, 39, 137–145. [Google Scholar]
  17. Sarwar, M.Z.; Park, J.-W. Bridge displacement estimation using a co-located acceleration and strain. Sensors 2020, 20, 1109. [Google Scholar] [CrossRef] [Green Version]
  18. Xin, J.; Zhou, J.; Yang, S.X.; Li, X.; Wang, Y. Bridge structure deformation prediction based on gnss data using Kalman-ARIMA-GARCH model. Sensors 2018, 18, 298. [Google Scholar] [CrossRef] [Green Version]
  19. Chen, Z.S.; Tse, T.K.; Liu, S.M.; Zhou, J.T.; Zeng, Y. Application of a self-adaptive Kalman filter approach in alignment control for an extra long span rail transit cable-stayed bridge. Struct. Infrastruct. Eng. 2017, 13, 1186–1197. [Google Scholar] [CrossRef]
  20. Cho, S.; Park, J.W.; Palanisamy, R.P.; Sim, S.H. Reference-Free Displacement Estimation of Bridges Using Kalman Filter-Based Multimetric Data Fusion. J. Sens. 2016, 2016, 3791856. [Google Scholar] [CrossRef] [Green Version]
  21. Zhang, H.; Zhang, L.S. Deformation prediction of large-span cable-stayed bridge based on Kalman filtering. J. Zhejiang Univ. Technol. 2021, 49, 650–655. [Google Scholar]
  22. Innocenzi, R.D.; Nicoletti, V.; Arezzo, D.; Carbonari, S.; Gara, F.; Dezi, L. A good practice for the proof testing of cable-stayed bridges. Appl. Sci. 2022, 12, 3547. [Google Scholar] [CrossRef]
  23. Nicoletti, V.; Martini, R.; Carbonari, S.; Gara, F. Operational modal analysis as a support for the development of digital twin models of bridges. Infrastructures 2023, 8, 24. [Google Scholar] [CrossRef]
  24. Yan, C.; Tong, Y.; Song, J.; Lu, B.; Wu, Q. Aerodynamic identification method for reentry vehicles based on Bayesian estimation theory. Sci. Sin. Phys. Mech. Astron. 2021, 51, 55–64. [Google Scholar]
  25. Wang, Y.W.; Zhang, C.; Ni, Y.Q.; Xu, X.Y. Bayesian probabilistic assessment of occupant comfort of high-rise structures based on structural health monitoring data. Mech. Syst. Signal Process. 2022, 163, 108147. [Google Scholar] [CrossRef]
  26. Liao, W. Key Issues in Bridge Structural Capacity Assessment Based on Health Monitoring System. Doctoral Dissertation, South China University of Technology, Guangzhou, China, 2016. [Google Scholar]
  27. Zhang, H.; Wu, E. Extreme distribution estimation method for temperature difference in large-span bridges considering parameter updating. Eng. Mech. 2017, 34, 124–130. [Google Scholar]
  28. Prakash, G. Probabilistic model for remaining fatigue life estimation of bridge components. J. Struct. Eng. 2021, 147, 04021147. [Google Scholar] [CrossRef]
  29. Yurtcu, M.; Kelecioglu, H.; Boone, E.L. The comparison of the scores obtained by Bayesian nonparametric model and classical test theory methods. Sci. Prog. 2021, 104, 00368504211028371. [Google Scholar] [CrossRef]
  30. Tidriri, K.; Chatti, N.; Verron, S.; Tiplica, T. Bridging data-driven and model-based approaches for process fault diagnosis and health monitoring: A review of researches and future challenges. Annu. Rev. Control 2016, 42, 63–81. [Google Scholar] [CrossRef]
  31. Li, Y.; Zhou, X.; Jia, C. Bayesian method and its application in predicting concrete carbonation depth. J. Cent. South Univ. (Sci. Technol.) 2014, 45, 3121–3126. [Google Scholar]
  32. Mao, S.; Tang, Y. Bayesian Statistics; China Statistics Press: Beijing, China, 2012. [Google Scholar]
  33. Zeng, W.; Zhuo, W.; Wang, D. Analysis of influencing factors on residual displacement index of RC bridge piers and Bayesian estimation. J. Vib. Shock 2021, 40, 145–150. [Google Scholar]
  34. Kelter, R. On the measure-theoretic premises of bayes factor and full bayesian significance tests: A critical reevaluation. Comput. Brain Behav. 2021, 5, 572–582. [Google Scholar] [CrossRef]
  35. Papadimitriou, C.; Papadioti, D.C. Component mode synthesis techniques for finite element model updating. Comput. Struct. 2013, 126, 15–28. [Google Scholar] [CrossRef]
  36. Tang, J.; Xiang, Z.; Feng, Q. Research and Practice of Extra-Large Span Continuous Rigid Frame Bridges—Chongqing Yangtze River Double-Line Bridge; People’s Communications Press: Beijing, China, 2008. [Google Scholar]
  37. Li, Y.; Liu, X.; Chen, Z.; Zhang, H. Model modification of cable-stayed bridge based on cable force response surface method. J. China Railw. Soc. 2021, 43, 168–174. [Google Scholar]
  38. Fu, B.; Yu, Y.; Wang, J. Model modification of continuous rigid frame bridges based on response surface method. J. China Foreign Highw. 2019, 39, 136–140. [Google Scholar]
  39. Ren, W.; Chen, H. Model modification of bridges based on response surface of finite element method. China Civ. Eng. J. 2008, 41, 73–78. [Google Scholar]
  40. Aistleitner, C.; Elsholtz, C. The Central Limit Theorem for Subsequences in Probabilistic Number Theory. Can. J. Math. 2012, 64, 1201–1221. [Google Scholar] [CrossRef] [Green Version]
  41. Khachatryan, L.; Boris, N. Nonlinear functionals preserving normal distribution and their asymptotic normality. Armen. J. Math. 2018, 10, 21–40. [Google Scholar]
  42. Strauss, A.; Frangopol, D.M.; Kim, S. Use of monitoring extreme data for the performance prediction of structures: Bayesian updating. Eng. Struct. 2008, 30, 3654–3666. [Google Scholar] [CrossRef]
  43. Wei, L.; Zhang, W. Bayesian Analysis; University of Science and Technology of China Press: Hefei, China, 2013. [Google Scholar]
Figure 1. The program of the finite element model modification based on the response surface method.
Figure 1. The program of the finite element model modification based on the response surface method.
Buildings 13 01556 g001
Figure 2. The determination of the prior information of the section internal forces in construction.
Figure 2. The determination of the prior information of the section internal forces in construction.
Buildings 13 01556 g002
Figure 3. Predicted values of segment elevation and section stress based on Bayesian updating.
Figure 3. Predicted values of segment elevation and section stress based on Bayesian updating.
Buildings 13 01556 g003
Figure 4. Cross-sectional view of concrete stress measurement points on the Clearwater River Bridge.
Figure 4. Cross-sectional view of concrete stress measurement points on the Clearwater River Bridge.
Buildings 13 01556 g004
Figure 5. Main beam cantilever construction beam section number (The number represents the construction beam section).
Figure 5. Main beam cantilever construction beam section number (The number represents the construction beam section).
Buildings 13 01556 g005
Figure 6. Transverse layout of stress measuring points of the Qingshuijiang Bridge section (Unit: cm).
Figure 6. Transverse layout of stress measuring points of the Qingshuijiang Bridge section (Unit: cm).
Buildings 13 01556 g006
Figure 7. The stress value of the top of the beam after the pouring of each segment of Section 2-2 of pier 5 left (The number represents the construction beam section).
Figure 7. The stress value of the top of the beam after the pouring of each segment of Section 2-2 of pier 5 left (The number represents the construction beam section).
Buildings 13 01556 g007
Figure 8. The stress value of the top of the beam after the tensioning of each segment of Section 2-2 of pier 5 left (The number represents the construction beam section).
Figure 8. The stress value of the top of the beam after the tensioning of each segment of Section 2-2 of pier 5 left (The number represents the construction beam section).
Buildings 13 01556 g008
Figure 9. The stress value of the top of the beam after the pouring of each segment of Section 4-4 of pier 6 left (The number represents the construction beam section).
Figure 9. The stress value of the top of the beam after the pouring of each segment of Section 4-4 of pier 6 left (The number represents the construction beam section).
Buildings 13 01556 g009
Figure 10. The stress value of the top of the beam after the tensioning of each segment of Section 4-4 of pier 6 left (The number represents the construction beam section).
Figure 10. The stress value of the top of the beam after the tensioning of each segment of Section 4-4 of pier 6 left (The number represents the construction beam section).
Buildings 13 01556 g010
Table 1. The measured value of the roof stress of the main beam cantilever construction control Section 2-2/4-4.
Table 1. The measured value of the roof stress of the main beam cantilever construction control Section 2-2/4-4.
Main Beam Cantilever in the Construction StageLeft 5# Pier Control Section 2-2Left 6# Pier Control Section 4-4
Stress after Pouring
(MPa)
Stress after Tensioning
(MPa)
Stress after Pouring
(MPa)
Stress after Tensioning
(MPa)
1#−0.40825−0.76325
2#−0.33725−1.3845
3#−2.28975−3.692
4#−3.56775−5.041
5#−4.26−6.51425
6#−4.828−6.51425
7#−6.47875−7.171
8#−6.44325−7.93425
9#−7.93425−8.53775−1.65075−2.39625
10#−7.739−9.28325−1.97025−3.28375
11#−8.67975−10.1885−3.124−5.2895
12#−9.35425−10.63225−4.544−6.3545
13#−9.46075−10.20625−5.254−7.40175
14#−9.6205−10.437−6.39−8.2005
15#−9.46075−10.66775−7.08225−8.53775
16#−9.7625−10.721−7.526−8.875
17#−9.92225−10.4725−7.597−8.165
Table 2. Bayesian update weights of control section stress in different construction stages.
Table 2. Bayesian update weights of control section stress in different construction stages.
SectionConstruction StageBayesian Updating PhaseWeight Coefficient
Section 2-2Concrete placementThe first update0.3497
The second update0.3923
Prestressed tensionThe first update0.3223
The second update0.3423
Section 4-4Concrete placementThe first update0.4444
The second update0.4589
Prestressed tensionThe first update0.4317
The second update0.4320
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Zhou, X.; Deng, T.; Chen, L.; Chen, J.; Li, A.; Yuan, Q.; Fang, W.; Gu, J. Application of Bayesian Update Method in the Construction Control of Continuous Rigid Frame Bridge Girders with High Piers and Large Spans. Buildings 2023, 13, 1556. https://doi.org/10.3390/buildings13061556

AMA Style

Zhou X, Deng T, Chen L, Chen J, Li A, Yuan Q, Fang W, Gu J. Application of Bayesian Update Method in the Construction Control of Continuous Rigid Frame Bridge Girders with High Piers and Large Spans. Buildings. 2023; 13(6):1556. https://doi.org/10.3390/buildings13061556

Chicago/Turabian Style

Zhou, Xiaolong, Taoxin Deng, Li Chen, Jie Chen, Ao Li, Qijie Yuan, Wei Fang, and Jianfeng Gu. 2023. "Application of Bayesian Update Method in the Construction Control of Continuous Rigid Frame Bridge Girders with High Piers and Large Spans" Buildings 13, no. 6: 1556. https://doi.org/10.3390/buildings13061556

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop